Overview
What it does:
- Opens an existing, submitted BOM (e.g., “BOM-Bottled Water-001”) and creates a new draft version
- Allows you to update header fields (quantity, warehouse, cost center), adjust raw material lines, and change operation steps (e.g., “Filling & Sealing,” “Labelling”)
- Links each update to the previous version—preserving historical records and version numbers
Prerequisites
- The BOM you want to update is already in Submitted (Active) status under
Manufacturing > Bill of Materials > BOM List - All raw materials and operations you need (e.g., “Filling & Sealing,” “Labelling”) are configured as stock items and workstations in the system
1.0 Open the Active BOM
- Navigate to
Manufacturing > Bill of Materials > BOM List. - Use the search bar or add filters—such as Item = “Bottled Water” or BOM No. = “BOM-Bottled Water-001”—to locate the BOM you want to update.
- Click the BOM’s name (e.g., BOM-Bottled Water-001). This opens the BOM form in view mode, showing tabs like Production Item, Operations, Scrap & Process Loss, Costing, etc.
2.0 Create a New Version (Amendment)
- In the BOM header (top-right), click New Version.
- A dialog appears asking for the Applicable From date—enter the date when the updated BOM should go into effect (e.g., today’s date).
- Click OK. A new draft BOM opens, prefixed with “**Amended from BOM-Bottled Water-001**.”
- Immediately click Save (top-right) to lock in the new version number and enable editing of header, materials, and operations.
3.0 Update Header Fields (If Needed)
- If your production batch size or warehouse changes, edit these fields:
- Quantity to Manufacture: Adjust if your standard run size has changed.
- UOM: Should remain the same (e.g., “Nos” or “Liters”), unless the fundamental unit has shifted. \
- Warehouse: Change the source raw material warehouse if procurement locations have shifted.
- Manufacturing Cost Center: Update if this BOM now ties to a different cost center.
- Any change to Quantity to Manufacture will automatically scale all raw material quantities in the Materials table when you next save.
4.0 Edit Operations (Using the “Operations” Tab)
- Click the Operations tab (as shown in the screenshot). You’ll see a list of existing operation rows, each with columns:
- No. (sequence number)
- Operation (e.g., “Filling & Sealing,” “Labelling”)
- Workstation Type (which machine or work center handles this step)
- Operation Time (time in minutes per unit, e.g., 0.500)
- Fixed Time (check if this step takes a flat time irrespective of quantity)
- Operating Cost (NGN) (calculated or entered cost per operation)
- To add a new operation:
- Scroll to the bottom of the operations table and click Add Row.
- Enter the next No. in sequence (e.g., if “Labeling” is No. 2, your new step becomes No. 3).
- In Operation, type or select the new operation name (e.g., “Carton Packing”).
- In Workstation Type, choose the appropriate workstation (e.g., “Packing Machine #2”).
- Enter Operation Time (e.g., 0.100 minutes per unit) and check Fixed Time if the step is a fixed duration (e.g., 5 minutes per batch).
- Optionally, adjust Operating Cost (NGN) if you track labor or machine cost directly in the BOM.
- To edit an existing operation (e.g., change time for “Labelling”):
- Click the cell under Operation Time (or Workstation Type, Fixed Time, Operating Cost) for that row.
- Change the value as needed (for example, update “Labelling” time from 0.060 to 0.075 minutes per unit).
- Press Enter or click outside the cell to confirm.
- To remove an operation:
- Check the box at the left of the row you want to delete.
- Click the trash-can icon that appears at the top of the operations table.
- Confirm the deletion if prompted.
- Once all operation edits are complete, click Save to validate the changes.
5.0 Edit Material Components (If Also Changing Components)
- Click the Production Item tab (or Materials table within the Production Item view).
- To add a new raw material:
- Click Add Row in the Materials table.
- Select the Item Code (e.g., “Bottle Caps”), enter the Required Qty (e.g., 1 cap per bottle), verify UOM, set Consumption Type (e.g., “Mandatory”), and confirm the Warehouse.
- To edit an existing component’s quantity:
- Click the cell under Required Qty for that item and enter the new amount (e.g., increase “PET Bottles” from 1 to 1.1 bottles per unit if packaging changed).
- If you updated Quantity to Manufacture in Step 3, click Save to auto-scale all component quantities proportionally.
- To remove a component:
- Check the box on the left of its row, then click the trash-can icon at the top of the materials table.
- After adjusting components, click Save again to confirm.
6.0 Review & Submit the Amended BOM
- Scroll back to the top of the BOM form to ensure:
- Header fields reflect the intended changes (e.g., new quantity, warehouse).
- The Materials table lists the correct raw materials and quantities.
- The Operations table shows updated or newly added steps with correct timings and costs.
- Click Submit at the top-right.
- The amended BOM is now Active, replacing the previous version as of the Applicable From date you set.
- CGIC will assign a new Revision Number (e.g., “BOM-Bottled Water-002”).
- All future Work Orders will reference this version of the BOM.