Prerequisites
- At least one submitted (active) BOM exists under
Manufacturing > Bill of Materials > BOM List. - You understand the basic structure of a BOM—components, quantities, operations, and costs.
- You have permission to create, amend, and view BOM records in the system.
1.0 Identify the BOM to Revise
- Navigate to
Manufacturing > Bill of Materials > BOM List. - Use the Search Bar or
Filter > Add Filterto find your active BOM (e.g., filter by Item = “Valdana Chocolate Bread”). - Confirm that the BOM’s Status is Submitted (active). You cannot directly edit a draft; only submitted BOMs can be revised.
2.0 Create a New Revision (Amend)
- Open the BOM you wish to revise by clicking its BOM No. (e.g., BOM-0001).
- In the BOM header, click New Version.
- A prompt appears asking for the “Applicable From” date.
- Enter the date when this new revision should become effective (e.g., today’s date if you want it active immediately).
- Click OK.
- CGIC generates a new draft version prefixed with “**Amended from BOM-0001**” and assigns it a new Revision Number (for example, BOM-0001-02).
- Click Save at the top-right to lock in the new revision number and enable editing of the header, materials, and operations.
3.0 Edit the New Revision
- With the draft revision open, make your changes to:
- Header Fields: Adjust Quantity to Manufacture, Warehouse, or Cost Center if needed.
- Materials Table: Add, remove, or edit raw material rows and quantities.
- Operations Tab: Insert new operation steps, modify times or costs, or delete obsolete steps.
- Scrap & Process Loss: Update expected scrap percentages.
- Costing Tab: Recalculate costs based on updated component rates or operation expenses.
- Click Save after each section to ensure data is validated.
4.0 Review and Submit the Revision
- Scroll to the top of the BOM form and verify:
- Applicable From date is correct.
- All updated components and operations reflect the intended changes.
- Costing results align with expectations (use Update Cost if necessary).
- Click Submit to finalize the new revision. The BOM status changes to Submitted (Active).
- The prior version (e.g., BOM-0001-01) remains in the system as a historical record but is no longer used for new production after the “Applicable From” date.
Once submitted, you cannot edit this revision. To make further changes, repeat Step 2 to create another amended version.
5.0 View Version History
- Open any BOM (active or historical) by going to
Manufacturing > Bill of Materials > BOM Listand clicking the desired BOM No. - In the BOM form, click
Menu > View History(often found at top-right or bottom of the form). - A pop-up lists all versions with:
- Revision No. (e.g., “BOM-0001-01,” “BOM-0001-02”)
- Modified By (user who submitted that revision)
- Modified On (timestamp of submission)
- Change Log (fields changed—e.g., “Required Qty for Flour changed from 10 kg to 12 kg”)
- Click any entry to open that specific revision in read-only mode for review.