Prerequisties
- Finished-goods item exists under
Stock > Item > Item List(with Is Stock Item checked).- A submitted (Active) BOM for that item exists under
Manufacturing > Bill of Materials > BOM List. - The BOM’s Applicable From date is on or before today, ensuring it is eligible for selection.
- A submitted (Active) BOM for that item exists under
- You have access to create or edit Work Orders under
Manufacturing > Work Order > Work Order List.- No conflicting Work Orders are already in process for this item (to avoid duplicate reservations).
1.0 Create a New Work Order
- Navigate to
Manufacturing > Work Order > New Work Order. - In the blank Work Order form, populate header details:
- Production Item: click the lookup and select the finished-goods item (e.g., “Danaval Chocolate Bread”).
- BOM: click the lookup and choose the desired BOM version. Only active BOMs appear.
- Quantity: enter the number of units you plan to produce (e.g., “500”).
- Company, Planned Start Date, Planned End Date, and Workstation (optional) as needed.
- Click Save to draft the WO. At this point, the BOM is linked and component details will be pulled when you generate the Material Request.
1.1 Verify BOM‐Driven Item Lines
- With the draft Work Order open, scroll to the Material Request or Items section.
- Click
Actions > Make Material Request(recommended) or Get Items from BOM:- CGIC pulls every component from the linked BOM, scales each component’s Required Qty by your WO quantity, and populates the MR or Items table.
- For example, if the BOM calls for 0.2 kg of flour per loaf and you set WO quantity = 500, CGIC auto-fills Flour Required Qty = 100 kg.
- Review the generated lines to confirm:
- Item Code and Description match BOM components.
- Required Qty is correctly scaled.
- UOM and Warehouse are accurate.
1.2 Adjust Operations (If Applicable)
- Click the Operations tab in the Work Order form.
- If BOM‐defined operations exist, click Get BOM Operations to populate the list of steps (sequence, workstations, planned time).
- Verify each row:
- Operation name aligns with the BOM.
- Workstation matches or adjust if a different machine should handle this run.
- Planned Time is correct based on the new quantity. CGIC scales time for per-unit steps, or uses Fixed Time for batch steps.
- Click Save.
1.3 Submit the Work Order
- After confirming materials and operations, click Submit at the top-right.
- The WO status changes to “Submitted”.
- CGIC reserves the scaled raw materials via Material Request.
- Operation times and workstations are locked in for scheduling.
- Downstream:
- Material Requests use BOM data to pull correct quantities.
- Stock Entries (Material Issue, Manufacture) reference the linked BOM for consumption and costs.
Linking Work Orders with the correct Bill of Materials in the CGIC App ensures that every production run uses the approved component list and operation sequence. By following these steps, you maintain consistency, automate material reservation, and enable accurate cost capture—driving reliable, repeatable manufacturing processes.