Prerequisites
Logged In & Role
-
-
- You’re logged into the CGIC App.
-
- Your role is Production Manager, Manufacturing User, or System Manager.
-
Stock & Production Data
-
-
- Component items have current on-hand and purchase rate information under
Stock > Item > Item List.
- Component items have current on-hand and purchase rate information under
-
-
-
- Work Orders exist (if you want usage data) under
Manufacturing > Work Order.
- Work Orders exist (if you want usage data) under
-
Items & BOMs
- At least one submitted (Active) BOM exists under
Manufacturing > Bill of Materials > BOM List. - All raw material and operation cost data are up to date in the BOM.
Permissions
- Ensure you have access to the Reports module and the
Manufacturing > Reportsmenu.
1.0 Access the Manufacturing Reports Menu
- From the main menu, navigate to
Manufacturing > Reports. - A list of BOM-related reports appears. Common report names include:
- BOM Costing Report
- BOM Material Requirement Report
- BOM Version History Report
- BOM Usage Report
2.0 Run the BOM Costing Report
- Click BOM Costing Report.
- In the filter panel, set:
- BOM: select the BOM you want to analyze (e.g., “BOM-Danaval-Chocolate-001”).
- Company: choose your legal entity (e.g., Charisma Global).
- Quantity: enter the production batch size (e.g., 500 units).
- Currency (optional): if multi-currency, select the currency for cost calculations.
- Click Refresh (or Run).
- The report displays:
- Raw Material Cost: sum of (Required Qty × Latest Buying Rate) for each component.
- Operation Cost: sum of (Operation Time × Operation Rate) for each step.
- Overhead/Additional Costs: any fixed or percentage-based charges defined in the BOM.
- Total Batch Cost and Cost per Unit.
- Review each line item’s cost contribution.
- To export, click
Download > CSVor Print to share with finance or management.
3.0 Run the BOM Material Requirement Report
- Click BOM Material Requirement Report.
- Set filters:
- BOM: select your target BOM.
- Quantity to Produce: enter the planned production quantity (e.g., 1,000 units).
- From Warehouse (optional): to check material availability in a specific location.
- Include Future Items (toggle): if you want to consider materials on pending Purchase Orders.
- Click Refresh.
- The report lists all raw materials with columns:
- Item Code & Description
- Required Qty (scaled for your batch)
- Available Qty (on-hand in the specified warehouse)
- Shortage Qty (if any)
- UOM and Warehouse
- Use this report to create Material Requests or Purchase Orders by clicking Create MR from the toolbar.
- Export with
Download > CSVor print to share with procurement.
4.0 Run the BOM Version History Report
- Click BOM Version History Report.
- Filter by:
- BOM: choose the base BOM number (e.g., “BOM-Danaval-Chocolate-001”).
- From Date / To Date: specify a date range to see revisions submitted within that period.
- Click Refresh.
- The report displays:
- Revision No. (e.g., “BOM-0001-01,” “BOM-0001-02”).
- Modified By and Modified On.
- Change Log Summary (fields changed, old vs. new values).
- Applicable From date for each revision.
- Click any Revision No. to open that historical BOM in read-only mode.
- Export or print to archive revision data for audits.
5.0 Run the BOM Usage Report
- Click BOM Usage Report.
- Set filters:
- BOM: select the BOM you want to investigate.
- Status (optional): filter Work Orders by status (e.g., “Completed,” “In Progress”).
- Date Range: define a period to see which Work Orders used this BOM.
- Click Refresh.
- The report shows:
- Work Order No. and Customer (if linked to a Sales Order)
- Production Quantity and Completed Quantity
- Workstation or Cost Center (where manufactured)
- Status of each Work Order
- Use this to identify how many units have been produced from a given BOM, and which orders remain open.
- Export with
Download > CSVor Print for production dashboards and capacity planning.