Prerequisites
Logged In & Role
-
- You are logged into the CGIC App.
Warehouse & Stock
- Relevant warehouses (e.g., “Raw Material Store,” “Central Warehouse”) are configured under
Stock > Warehouse. - -On-hand stock records are up to date (all Purchase Receipts, Stock Entries, etc. are submitted).
Items & BOMs
-
- Finished‐goods item and all raw‐material items exist under
Stock > Item >Item List. - A submitted (Active) BOM for the finished product is available under
Manufacturing > Bill of Materials > BOM List.
- Finished‐goods item and all raw‐material items exist under
1.0 Open the BOM Material Availability Report
- Navigate to
Manufacturing > Reports > Material Availability. - The Material Availability interface opens, showing two main filters:
- BOM: select the BOM you plan to execute (e.g., “BOM-Danaval-Chocolate-001”).
- Quantity to Produce: enter the planned production quantity (e.g., 500 units).
- Click Refresh (or Run) to generate a real-time comparison between BOM requirements and available stock.
2.0 Interpret the Availability Dashboard
- The top section displays a summary:
- Total Required Qty (for each component, based on the entered production quantity)
- Total On-Hand Qty (sum of current stock across selected warehouses)
- Shortage Qty (difference: Required − On-Hand, if any)
- The Materials Table lists each raw material with columns:
- Item Code & Description
- Required Qty (for this run)
- Available Qty (real-time on-hand in the chosen warehouse(s))
- Shortage Qty (when Available < Required)
- Warehouse (default source location per BOM; optional filter to view other warehouses)
- If all Shortage Qty values show 0, you have sufficient stock to execute the BOM. If any Shortage Qty is positive, you need to procure or transfer that quantity before scheduling production.
y default, the report checks all warehouses you have access to. Use the Warehouse Filter to restrict the view to a specific location if needed.
3.0 Drill Down into Specific Item Shortages
- In the Materials Table, click on the Item Code of any component flagged with a shortage.
- A pop-up or new tab opens the Stock Ledger for that item, filtered by relevant warehouses, showing:
- Recent Receipts (dates and quantities)
- Recent Issues (sales, transfers, picks)
- Pending Material Requests or Reserved Quantities
- Use this detail to identify if incoming stock is on the way (e.g., Purchase Orders in-transit) or if reallocation from another warehouse is possible.
4.0 Create or Update Material Requests for Shortages
- From the Material Availability report, click Create Material Request (button usually located at the top-right or in the toolbar) to open a pre-filled MR form.
- In the new Material Request form:
- Request Type: automatically set to “Manufacture”.
- BOM: pre-selected based on your report choice.
- Quantity: mirrors the Quantity to Produce used in the report.
- Items table: lists only the components with Shortage Qty > 0, with Required Qty equal to the shortage amount and Available Qty showing zero or insufficient stock.
- Confirm or manually adjust any Warehouse assignments if you plan to source from multiple locations.
- Click Save, then Submit to log a Material Request. If you need to send Purchase Orders immediately, click
Create > Purchase Orderfrom the MR toolbar.
5.0 Plan Inter-Warehouse Transfers (If Applicable)
> If shortages exist only in the default “From Warehouse” but another warehouse has sufficient stock, you can transfer instead of purchasing.- In the Materials Table, click Available Qty for a component to view bin/warehouse breakdown.
- Note the warehouse(s) with surplus stock.
- Create a
Stock Entry > New Stock Entrywith Purpose = Material Transfer:- Item Code: the component.
- Qty: amount to move (up to surplus).
- Source Warehouse / Bin: where stock resides.
- Target Warehouse: the BOM’s default source.
- Click Save, then Submit to move stock.
- Return to Material Availability report and click Refresh to confirm that the shortage has been resolved.
You may need to repeat Steps 3 and 4 for multiple components if sourcing across warehouses.
6.0 Final Verification Before Work Order Creation
- Once all Shortage Qty values read 0 in the Materials Table, your materials are fully available.
- Navigate to
Manufacturing > Work Order > New. - Select the same BOM and re-enter the Quantity to Produce you used in the Material Availability report.
- Confirm that the Material Availability Warning no longer appears at the top of the Work Order form.
- Click Save, then Submit to queue the Work Order—confident that production can proceed without raw material interruptions.
By monitoring material availability against your BOM requirements in the CGIC App, you eliminate guesswork and ensure production runs are fully supported by inventory on hand or in process. This proactive approach prevents unplanned downtime, aligns procurement and planning teams, and keeps your manufacturing schedule on track.